Summer 2026 Help

Adding New Milestones for Design Projects

Purpose

As a Project Owner, you can add Plan, Development, Verify & Validate, and Design Transfer milestones to mark key completion points in the product design project.

Prerequisites

Installation Package: CQ Core, CQ Design Extension, CQ Management Review Dashboard Extension

Product: ProductQuest

Function: Design Projects

User Profile: Standard User

Permissions: CQ Base User PSG, CQ Design Owner PSG

Record Status: Draft, Open


Steps

  1. Open the Project record.

  2. Open the Deliverables tab.

  3. Select New Milestone from the Quick Action Menu to add milestones for any stages listed.

  4. Specify this information:

    • Title
      Provide the name of the New Milestone.

    • Description
      Provide what the New Milestone is about.

    • Assignee
      Specify the person responsible for the completion of New Milestone. Assignee must be a Team Member with Editor access.

    • Status
      If applicable, specify the Status.

    • Progress
      If applicable, specify the Progress percentage.

    • Due Date
      Specify the Due Date.

    • Start Date
      Specify the Start Date to start working on the New Milestone.

    • End Date
      Specify the End Date, if it is known at this time. (This field may be updated later by the Project Owner when the New Milestone is completed.)

  5. If applicable, provide the Comments.

  6. If applicable, specify the Controlled Document records associated with the New Milestone.

  7. Click Save.

Expected Outcome

  • New Milestone is added to the Plan/Development/Verify& Validate/Design Transfer Stage.

  • New Milestone Edit and Delete options are available.


Additional Resources

ComplianceQuest


💡

We Value Your Feedback

To provide feedback or suggestions to improve the help content on this page click here.